HOWIE'S LOFT UPDATE

Goal: $40,000,000

Dear Church Family, LOFT Update. We are currently week 28 into construction. Our target completion date remains September 24, 2024. To date, the following construction items have been completed: soil excavation processing and compaction; 176 piers drilled and poured from 30’ to 71’ deep (4 remain to be drilled); erection of sequence 1 and 2 of steel (out of 15 sequences); slabs poured on the East Foyer, College Department and Sports Court 1; storm sewer replaced; and foundational grade beams poured between piers. This week, steel continues to be erected, concrete walls are being formed and poured, and elevator and stairwell construction begins. As of today, we need to collect $5.34 million to reach our ultimate goal of $40 million. We are